| The Mulkey Family Home
Build #28 |
 |
John & Jane
Mulkey |
|
Map
to Build Site |
| week |
scheduled
tasks |
photos |
| Prebuild |
Foundation |
prebuild
|
| July 13 |
Flooring system (SPMs
only) |
week 1 |
| July 20 |
Exterior walls |
week 2 |
| July 27 |
Interior walls, roof trusses |
week 3 |
| Aug 3 |
Roofing, front porch |
week 4 |
| Aug 10 |
Porch, siding prep |
week 5 |
| Aug 17 |
Insulation, siding |
week 6
no photos |
| Aug 24 |
Siding, porch roof, soffits |
week 7 |
| Aug
31 |
Labor
day - no work |
|
| Sept 7 |
Interior molding, painting, soffits |
week 8
no photos |
| Sept 14 |
Painting |
week 9 |
| Sept 21 |
Painting, Interior trim |
week 10 |
| Sept 28 |
Exterior details, cabinets & closets |
week 11 |
| Oct 5 |
Flooring prep, punch list |
week 12
no photos |
| Oct 12-Nov 23 |
No work - contractor
delays... |
|
| Dec 7 |
Landscaping |
week 13
no photos |